PAYMENT SCHEDULE to the Project is as follows
On blocking
Before sigining the agreement (20% less Blking Amt) – 20%
Commencement of Foundation – 5%
completion of basment slab – 5%
Completion of ground floor slab – 6%
completion of 2nd Floor slab – 6%
Completion of 4th Floor Slab – 6%
Completion of 6th Floor slab – 6%
Completion of 8th Floor Slab – 6%
completion of 10th Floor Slab – 6%
Completion of 12th Floor Slab – 6%
Completion of 14th Floor Slab – 6%
Completion of 16th Floor Slab – 6%
Completion of Top floor roof slab – 6%
Block work/ masanery of respective unit – 6%
Flooring of the respective unit – 3%
Handing over – 1%